East Devon sewage spills’ hot spot is revamped amid water giant’s £750million bid to do better

An East Devon hot spot responsible for hundreds of sewage spills has been revamped, reducing future risk South West Water (SWW) has confirmed.

Work to reduce storm overflow spills has been carried out at Honiton Wastewater Treatment Works after 219 were recorded at the site in 2024.

The number of sewage spills marked the site among the worst offenders across Devon and Cornwall.

The water giant, who revealed part of the work included relining 525 metres of sewer, said the result has been a drop in sewage spills to 31 so far in 2025.

The work finished in January 2025 and included improvements made to 23 manhole covers, to prevent groundwater from entering the sewer network.

SWW

Pictured here is the new lining being inserted.
Photo: SWW.

Charlie Ford, SWW project manager for Honiton, said: “We’re really pleased with the results of the work we completed earlier this year and the impact it’s having on our spill performance so far.

“Keeping groundwater out of our sewers helps to free up space within our wastewater treatment works and makes a real positive impact on the local environment here in Honiton and across the region where similar work is being carried out.”

sewer

Pictured here is the newly-lined sewer.
Photo: SWW.

The Honiton Wastewater Treatment Works was found to be one of SWW’s ‘top 10 spilling sites’.

SWW is spending £750million over the next five years in a bid to be the first water company to beat the Government’s 2040 target by a decade of achieving fewer than 10 annual spills per overflow.

A spokesperson for the company said: “South West Water has completed work to reduce storm overflow spills from one of its top 10 spilling sites after relining over 500 metres of sewer.

“Honiton Wastewater Treatment Works in Devon saw 219 storm overflow spills in 2024, making it the 10th highest spilling site across Devon and Cornwall.

“Following interventions from South West Water, which included relining 525 metres of local sewer, this number has dropped to 31 spills in 2025 so far.

“The work, which was completed in January 2025, also saw improvements made to 23 manhole covers to prevent groundwater from getting into the sewer network.”

Honiton

CCTV surveys were carried out as part of the works.
Photo: SWW.

The company said relining sewers reduces the amount of groundwater entering the local network during wet weather which can otherwise overwhelm the treatment works and lead to a storm overflow spill.

The SWW spokesperson added: “An initial inspection of the sewers is carried out by CCTV surveys to identify areas that may be impacted by groundwater.

“Affected areas are then thoroughly cleaned so the lining material can be pulled through the inside of the pipe and laid in place.

“The lining is then cured inside the sewer to provide a watertight protective seal before further CCTV surveys are used to confirm the lining has set as required.”